How to Install a Weir Box

While Weir Boxes eliminate many of the typical installation considerations of Weir Plates, some considerations have to be taken into account when installing a Weir Box.

Installing the Weir BOX

  • The Weir Box must be mounted so that the weir plate is level from front-to-back and from side-to-side.
  • The mounting surface of the weir box should be sufficiently consolidated that it will not shift or move out of position due to settlement, frost heave, etc.
  • The weir crest must be horizontally level.
  • If present, the bevel of the weir crest must be set downstream.
  • In earthen channel applications, the channel downstream of the Weir Box should be reinforced / armored so that scour does not occur.  Scouring can lead to the Weir Box shifting out of position.  